Orange Barrel Alert: Road Construction Underway In Portage
Your definitive guide for the City of Portage's road construction projects. See when work will begin and when it is expected to wrap up.
West Milham Avenue (Oakland Drive to South Westnedge Avenue) – new mast arms at the Oakland and Constitution intersection, right turn lane for the Portage Northern/North school complex at Constitution, ADA ramp upgrades, mill and resurface.
Estimated Construction Cost: $2,400,000
Anticipated Start Date: April 2019
Anticipated Completion Date: Fall 2019
Romence Road (Oakland Drive to Constitution Boulevard) – water main replacement, ADA ramp upgrades, mill and resurface.
Estimated Construction Cost: $1,500,000
Anticipated Start Date: April 2019
Anticipated Completion Date: Fall 2019
Lovers Lane (East Centre Avenue to East Milham Avenue) – realignment of the reverse curve north of Ramona Avenue, reduction from four lanes to a three-lane configuration with bike lanes, mill and resurface. (Project limit starts 150’ south of East Centre Avenue and end 300’ north of East Milham Avenue).
Estimated Construction Cost: $1,150,000
Anticipated Start Date: April 2019
Anticipated Completion Date: July 2019
Idaho Avenue (Oregon Avenue to South Westnedge Avenue) – water main replacement, full road reconstruction with storm drainage improvements, curb and gutter, sidewalk.
Estimated Construction Cost: $1,900,000
Anticipated Start Date: April 2019
Anticipated Completion Date: Fall 2019
Zylman Avenue (Portage Road to South Sprinkle Road) – replacement of force main, new boulevard road section east of Cox's Drive with roundabout at Cox's Drive and 10’ wide bike path east of Cox's Drive
Estimated Construction Cost: $3,100,000
Anticipated Start Date: June 2019
Anticipated Completion Date: Fall 2019
Portage Road/Lakeview Drive Intersection Realignment – realignment of the intersection of Lakeview Drive at Portage Road to approximately 150’ south, including curb and gutter, sidewalk, ADA ramps, storm drainage improvements and the construction of Lakeview Court cul-de-sac.
Estimated Construction Cost: $550,000
Start Date: Fall 2018
Status: Removal of trees and brush complete.
Anticipated Completion Date: Summer 2019
Angling Road (Vincent Drive to north city limits) – storm drainage improvements, ADA ramp upgrades, mill and resurface.
Estimated Construction Cost: $375,000
Anticipated Start Date: June 2019
Anticipated Completion Date: Fall 2019
Meredith Street (South Sprinkle Road to East Kilgore Road) – extension of sidewalk on west side, mill and resurface.
Estimated Construction Cost: $260,000
Anticipated Start Date: June 2019
Anticipated Completion Date: Fall 2019